FAR 33.211 says the contracting officer’s decision timeline accounts for the adequacy of the contractor’s data. Your documentation is not just evidence. It is on the clock.
A certified claim is a document package with a legal wrapper. The wrapper gets the attention; the package decides the outcome.
The clocks, precisely
Under FAR 33.211 the threshold that governs everything is $100,000.
- For a claim of $100,000 or less, the contracting officer must issue a decision within 60 days of receiving a written request from the contractor for a decision within that period. Absent such a request, the decision is due within a reasonable time after receipt of the claim.
- For a claim over $100,000, the decision is due 60 days after receiving a certified claim — or, if that is not possible, the contracting officer must notify the contractor within those 60 days of the date a decision will issue.
- FAR 33.211(d) directs that a decision issue within a reasonable time, taking into account the size and complexity of the claim, the adequacy of the contractor’s data, and other relevant factors.
- Under FAR 33.211(g), failure to issue a decision within the required period will be deemed a decision denying the claim and authorizes an appeal or suit.
Read (d) again. The adequacy of your data is written into the standard by which the contracting officer’s own delay is judged. A thin submission does not just lose on the merits — it legitimizes the delay.
The certification trap
FAR 33.211(e) provides that where a claim exceeds $100,000 and the certification is defective, the contracting officer has no obligation to issue a final decision if, within 60 days of receipt, they notify the contractor in writing of the reasons the certification is defective.
So a defective certification does not merely delay the claim. It can stop the clock entirely while you fix it, and the fix restarts the sequence.
After the decision
The decision itself must carry appeal-rights language. Under FAR 33.211(a)(4)(v) the contractor must act within 90 days from the date it receives the decision to appeal to the agency board of contract appeals, or may bring an action within 12 months of receipt in the Court of Federal Claims.
The board’s small claim procedure applies to claims of $50,000 or less, or $150,000 or less for a small business. Its accelerated procedure applies to claims of $100,000 or less. Which procedure you are in shapes how much documentation you will actually be able to put in front of the tribunal.
What the package has to do
- Establish entitlement from the contract documents — the clause, the modification, the direction that caused the change
- Prove causation with contemporaneous records rather than reconstruction, which means correspondence, schedules, daily reports and meeting notes, dated and in sequence
- Quantify with cost records that tie to the accounting system, not to a spreadsheet built for the claim
- Be internally consistent — the narrative, the schedule analysis and the cost exhibits must agree, and this is where most packages fail
- Be numbered and indexed so the contracting officer, and later a board, can find any cited document immediately
Where we fit
We assemble, number, index and produce the record. Counsel drafts the claim, signs the certification and makes every legal judgment in it. We do not certify, and we do not decide what is entitled — but we do make sure the exhibit that the narrative cites actually says what the narrative says it says, which is a reconciliation nobody enjoys doing under deadline.
What we do
Pro-Legal Services, Inc. provides Contract Disputes Act claim support to contractors and their counsel from Arlington, Virginia — contemporaneous record assembly, cost exhibit reconciliation, numbering and indexing built for a board record, and production on the claim’s timeline.
Small business, minority-owned, SAM registered, prime or subcontractor.
Related: request for equitable adjustment documentation, Court of Federal Claims litigation support, government contracts litigation support, DCAA audit document support, termination for convenience settlement proposal, administrative record preparation, exhibit indexing services.
Pro-Legal Services, Inc. supports claims from Arlington, Virginia, minutes from the Court of Federal Claims and the agency boards, for contractors nationwide.
Claim going in against a 60-day clock? Send us the record you have. The reconciliation between narrative and exhibits is the thing worth doing before it is filed, not after. Pro-Legal Services, Inc. · 1550 Wilson Blvd, Suite 250, Arlington, VA 22209 · 202-955-9400 · info@pro-legal.com